conclusion of the contract. however, if the circumstances so indicate, the risk is assumed by the buyer from the time the goods were handed over to the carrier who issued the documents embodying the contract of carriage. nevertheless, if at the time of the conclusion of the contract of sale the seller knew or ought to have known that the goods had been lost or damaged and did not disclose this to the buyer, the loss or damage is at the risk of the seller.
article 69
(1) in cases not within articles 67 and 68, the risk passes to the buyer when he takes over the goods or, if he does not do so in due time, from the time when the goods are placed at his disposal and he commits a breach of contract by failing to take delivery.
(2) however, if the buyer is bound to take over the goods at a place other than a place of business of the seller, the risk passes when delivery is due and the buyer is aware of the fact that the goods are placed at his disposal at that place.
(3) if the contract relates to goods not then identified, the goods are considered not to be placed at the disposal of the buyer until they are clearly identified to the contract.
article 70
if the seller has committed a fundamental breach of contract, articles 67, 68 and 69 do not impair the remedies available to the buyer on account of the breach.
chapter v
provisions common to the obligations of the seller and of the buyer
section i. anticipatory breach and instalment contracts
article 71
(1) a party may suspend the performance of his obligations if, after the conclusion of the contract, it becomes apparent that the other party will not perform a substantial part of his obligations as a result of:
(a) a serious deficiency in his ability to perform or in his creditworthiness; or
(b) his conduct in preparing to perform or in performing the contract.
(2) if the seller has already dispatched the goods before the grounds described in the preceding paragraph become evident, he may prevent the handing over of the goods to the buyer even though the buyer holds a document which entitles him to obtain them. the present paragraph relates only to the rights in the goods as between the buyer and the seller.
(3) a party suspending performance, whether before or after dispatch of the goods, must immediately give notice of the suspension to the other party and must cont